Resource metadata

Field Value
Data last updated November 22, 2021
Metadata last updated November 22, 2021
Created November 22, 2021
Format PDF
License CC-BY-SA-4.0
Data collection infoMonitoring is conducted by the Regional District of Central Kootenay. Flow depth through the aluminum flow monitoring weir is measured by an ultrasonic level transmitter. Raw water turbidity is monitored online in the treatment plant. pH is hand measured when water technicians are onsite at the Ymir water treatment plant. A treated water sample is taken weekly for Total Coliforms, and E.coli bacteria testing. Testing is provided by the BC Centre for Disease Control through Interior Health.
Data processingThe Kindsvater‐Carter Formula was adopted to calculate flow through the sharp crested aluminum weir installed in the concreate water system intake weir, this formula is detailed in the report. An Excel pivot table was used to present the follow daily average weir flow level, creek flows and turbidity data.
Data typenon-lab
Has viewsTrue
Hash6295959745c1e960762ae88549f25458
Id6a942a21-e545-40d7-b2bf-82642cf3ba15
Mimetypeapplication/pdf
On same domainTrue
Package id248f1f4d-e1ea-42fe-9f11-db0a6b614cbb
Resource citationRegional District of Central Kootenay (2021). 2020 Quartz Creek Flow and Water Quality Monitoring Report. Columbia Basin Water Hub (Resource). Nelson, BC. (DOI).
Resource data disclaimerNo warranty or guarantee exists that the information is accurate, complete, current, or suitable for any purpose. The individual user must confirm the accuracy of the data and whether it will be appropriate for their purpose.
Resource locationThe Ymir water system is located in the community of Ymir between Nelson and Salmo, within RDCK Electoral Area G.
Size1 MiB
Stateactive
Url typeupload
Waterhub certifiedCertified
Waterhub gradePeople and Perspectives
upload
Citation (Required) Regional District of Central Kootenay (2021). 2020 Quartz Creek Flow and Water Quality Monitoring Report. Columbia Basin Water Hub (Resource). Nelson, BC. (DOI).
Resource Location The Ymir water system is located in the community of Ymir between Nelson and Salmo, within RDCK Electoral Area G.
Data Collection Information Monitoring is conducted by the Regional District of Central Kootenay. Flow depth through the aluminum flow monitoring weir is measured by an ultrasonic level transmitter. Raw water turbidity is monitored online in the treatment plant. pH is hand measured when water technicians are onsite at the Ymir water treatment plant. A treated water sample is taken weekly for Total Coliforms, and E.coli bacteria testing. Testing is provided by the BC Centre for Disease Control through Interior Health.
Data Processing The Kindsvater‐Carter Formula was adopted to calculate flow through the sharp crested aluminum weir installed in the concreate water system intake weir, this formula is detailed in the report. An Excel pivot table was used to present the follow daily average weir flow level, creek flows and turbidity data.
Data Disclaimer No warranty or guarantee exists that the information is accurate, complete, current, or suitable for any purpose. The individual user must confirm the accuracy of the data and whether it will be appropriate for their purpose.
Water Hub Data Grade People and Perspectives
Date of Most Recent Water Hub QA/QC
Loading Status
Datastore Status
Data type General

Site

No data available

Parameter

No data available